← All projects
Power generation · Bani Suef
Bani Suef Combined Cycle — Steam Turbines
Main, auxiliary, and monorail systems for steam-turbine and generator-annex buildings.
- Owner
- Ministry of Electricity and Renewable Energy
- Contractor
- Elsewedy Electric
- Equipment brand
- Meloni
Equipment scope
The recorded lifting package.
- 01
2 steam-turbine building cranes — 140/25 t capacity
- 02
2 steam-turbine building cranes — 80/25 t capacity
- 03
2 steam-turbine building monorails — 5 t capacity
- 04
2 generator-annex building cranes — 10 t capacity
Delivery record